“The following product development project is scheduled to commence next month at MultiCare. The project activities, their resource requirements for team members,and precedence relationships are listed in the table below. Note that only one type of resource is used by each activity: team members. There are five team members assigned to this project. Given a resource constraint of five team members and a schedule found using the minimum slack heuristic, which activity should be scheduled after activity A?”